Asbestos survey before a renovation or demolition in Washoe County
In Washoe County the asbestos paperwork comes before the building permit, not after. The agency in charge is the Air Quality Management Division (AQMD) of Northern Nevada Public Health (NNPH). This page puts its published requirements in the order you will meet them. It is a plain-language summary from an independent information site. The agency's own pages are linked throughout and are the authority.
This number goes to a recorded voicemail box. No one answers live and, for now, no one calls back.
You will hear a notice that the call and your message are recorded, and that notice is part of the recording. If you do not want to be recorded, hang up during the notice or email the address on our privacy page. This site does not work with or refer callers to any asbestos testing company yet, so the fastest route to service today is to contact a licensed company directly.
Recorded voicemail line: (775) 458-7912
Does your project need an Acknowledgement of Asbestos Assessment?
The Acknowledgement of Asbestos Assessment, or AAA, is the document the building department looks for. Washoe County's demolition permit application calls it the "pink slip" from Air Quality (Washoe County demolition application).
| Project | AAA needed? | Source |
|---|---|---|
| Complete demolition of any building, including a single-family home | Yes, before the building permit | NNPH Asbestos Program |
| Renovation at a regulated facility, including a roof tear-off | Yes, unless the disturbance is under the stated threshold | NNPH Asbestos Program |
| Remodel of a single-family home, not part of a larger project | Generally no | NNPH asbestos FAQ, Plan Review |
| Build-out with no demolition or disturbance shown in the plans | No | Plan Review |
What counts as a regulated facility
Most structures do. Residential buildings with four or fewer dwelling units are excluded from the definition. Two cases bring a house back in: a single-family home demolished to make way for a commercial project or new construction, and a group of residential buildings under one owner on one site, which the county treats as a single installation (NNPH asbestos FAQ).
If you are not sure which row you are in, ask AQMD in writing before you apply for the permit: AQMDAsbestos@nnph.org or (775) 784-7200.
Step 1: the survey
A survey has to be completed before you apply for the AAA. The county's requirements are specific:
- It must be done by an AHERA Certified Building Inspector. AQMD does not perform surveys or sampling.
- It must cover the materials the work will disturb, including materials on the outside of the structure.
- The survey requirement applies whatever the length, area or volume to be disturbed.
Source: NNPH Asbestos Program.
The county's FAQ lists the kinds of material that trigger a survey when they will be disturbed: wall systems, flooring, pipe insulation, cement products such as Transite, roofing and structural concrete (NNPH asbestos FAQ).
A newer building is not exempt. The county's reasoning is that most of the 1989 federal ban was overturned, so many asbestos products stayed legal to sell, and only sampling can settle the question (NNPH asbestos FAQ).
Who you can hire
NNPH publishes a list of local AHERA Certified Building Inspectors on its Asbestos Program page and notes that it may not include every operator. Separately, Nevada requires a state license for anyone offering asbestos consultant services (NAC 618.927). Ask for both credentials in writing.
The firm that surveys should not be the firm that removes. Nevada's rules bar a licensed abatement contractor from acting as inspector or consultant on its own project unless the state grants an exemption (NAC 618.918).
Step 2: the AAA application
Apply online through the Accela One regional permits portal. NNPH says online is the preferred and fastest route. Mail, email and the drop box are slower. A complete application is processed within 10 business days (NNPH Asbestos Program).
What the county says it typically wants uploaded (Washoe County 311):
- the demolition sheet from your plans
- the sampling report with laboratory results and chain of custody
- a floor plan showing where each sample was taken
- anything else relevant, such as photographs
An incomplete survey report is the usual reason an application stalls, so check the report against that list before you pay the final invoice.
Step 3: the building permit
The AAA goes to whichever building department covers the address: City of Reno, City of Sparks or Washoe County. Those departments may route your plans to AQMD for review or ask screening questions at intake (Plan Review).
Step 4: notification, at least 10 working days ahead
Two kinds of notification exist (NNPH Asbestos Program):
- Demolition. Required for any building demolition, single-family homes included, even when the survey finds no asbestos.
- Renovation. Required when regulated asbestos-containing material above these amounts will be removed: 260 linear feet on pipes, 160 square feet on other components, or 35 cubic feet where length and area cannot be measured.
Either one must be submitted at least 10 working days, which is two full weeks, before the work starts. The county's FAQ adds three details that catch people out:
- The waiting period starts only when a complete notification is received or postmarked. A notice with a missing fee, date or quantity does not start the clock.
- The owner or the contractor can file, and either can be held responsible if the notice is inadequate.
- Once more than a threshold amount has been removed at a facility in a calendar year, later work that year needs notification even if it is smaller (Washoe County 311).
The county does not publish the fee amount on the pages linked here. Ask AQMD for the current fee schedule.
Step 5: removal
Regulated material has to be removed by a licensed asbestos abatement contractor before the renovation or demolition disturbs it (NNPH Asbestos Program, NAC 618.9155). NNPH also advises contacting Nevada OSHA about its own requirements for disturbing asbestos-containing materials, which are separate from the county's.
Planning the calendar
Add the published waiting periods together before you set a start date:
- survey and laboratory turnaround: ask the inspector
- AAA processing: up to 10 business days once the application is complete
- notification: at least 10 working days before work starts
Whether the AAA review and the notification period can overlap on your project is a question for AQMD.
Emergencies and cancellations
For a qualifying emergency renovation, the county no longer requires a separate waiver request. The application is submitted with its emergency section completed, with payment, before work starts when possible. After-hours emergencies can be notified on the next working day. If a notified project is canceled, the county asks for a copy of the original notification marked as canceled (NNPH asbestos FAQ).
Where the rules come from
- Federal: National Emission Standard for Asbestos, 40 CFR Part 61, Subpart M (EPA overview)
- Local: District Board of Health Regulations Governing Air Quality Management, Parts 040.110 and 040.115 (NNPH Asbestos Program)
- State: Nevada Administrative Code 618.850 to 618.986 (NAC 618.9155)
AQMD's mailing address is 1001 E. Ninth Street, Suite B-171, Reno, NV 89512.
This page was last checked against those sources on November 11, 2026. Rules change. Confirm with AQMD before you rely on any of it for a permit.